Shenzhou homeland brings you to understand the calculation of home improvement period calculation

Whether it is self-made home decoration design or home improvement company to decorate the design, the home improvement period is a factor that many owners attach great importance to. The length of the home renovation period is too long and will have a big impact on the check-in time. Therefore, the rationality of the renovation schedule is particularly important. Let's take a look at the decoration schedule with the Shenzhou home plate. How long is the home improvement period for each project?

The layout of the home improvement schedule is as follows:

First, before the start of construction

1. At least 10 days before starting work:

Make design plans, select decoration companies, propose renovation contents and requirements; conduct field measurement related data, draw detailed drawings; communicate with designers to determine the final home improvement plan.

2. At least 5 days before starting work:

Look at the budget to sign the contract; determine the materials to be used; make a preliminary budget for the home improvement costs, compare it with the budget of the home improvement company; sign the renovation contract.

3. At least 2 days before starting work:

Prepare before entering the venue; contact the property department to complete the necessary procedures; greet the neighbors; arrange the door and window materials and auxiliary materials to enter the site; hand over to the construction party key; pay the first installment.

Second, after the start of construction

1. 1-2 days after the start of construction: knock the wall to change the structure.

2, start work 5-10 days: Anhui pipe installed circuit; pipeline material processing acceptance; concealed project acceptance.

3, 10-20 days after the start of construction: tiled wall surface; mud and tile engineering acceptance; acceptance of wall materials, such as wall paint, ceramic tiles, etc.

4, start work 20-30 days: do woodworking, painting; paint materials into the field acceptance; woodwork project acceptance.

5, start work 30-50 days: floor to do kitchen and bathroom equipment; floor materials acceptance; cabinet installation and acceptance; bathroom products on site, installation and acceptance; buy back electrical appliances and installation; bathroom products on site installation and acceptance.

6. Start work for 50-60 days: Carry out the final acceptance and make a final settlement for the final settlement.

Third, the decoration schedule arrangements note:

a. The renovation schedule should be detailed, such as including various construction projects, construction time and personnel.

b. The owner can ask the decoration company for the decoration schedule, basically understand the arrangement in the home decoration period, such as the renovation of the water circuit, the sealing of the wood, the paste of the tile, the production of the ceiling keel and so on. In this way, the owner can arrange his or her own time and go to the site to conduct quality inspections at regular intervals.

c. The required construction period is different for different room types, areas and construction contents. In general, oil workers are more time-consuming and should not be too rushed. The normal construction period should be controlled within 45 days. The general two-bedroom level can be completed in 40 days, but it is not very plentiful. It is necessary to arrange the process and main materials.

Above we have briefly understood the total length of the home improvement period before and after the start of the renovation schedule. Some renovation processes require the owner to urge the decoration company to comply with the renovation schedule, but some home improvement designs are indeed time consuming and should not be too rushed.

Oil-Control Nourishing Spray

OIL- CONTROL NOURISHING SPRAY
Key ingredients: PCA sodium,
erythritol, carrageenan, pea
extract, hydrolyzed rice protein,
etc.
Capacity: 100ml
t It is suitable for daily scalp
maintenance of oily hair, or it can
be used with platinum version or luxury version
-HERBAL EXTRACT-


Oil Control Spray,Hair Oil Control,Scalp Balancing Fluid,Hair Fall Control Oil

Shenzhen Sipimo Technology Co., Ltd , https://www.sipimotech.com